The court found that the environmental impact assessments had failed to consider emissions from burning the fields’ output alongside those from other approved production on the Norwegian continental shelf, according to the source material.
Government attorney Fredrik Sejersted told NTB that the ruling did not terminate the companies’ permits. The authorities must instead carry out fresh assessments and reconsider the approvals. The companies were not parties to the proceedings, and the ruling’s legal effect applies to the state.
Aker BP communications director Tore Langballe told E24, as reported by Nettavisen, that the company retained its target of starting production at Yggdrasil in summer 2027. Aker BP also intends to review the judgment and contribute to the subsequent work on the impact assessments.
Equinor media contact Morten Eek told EnergyWatch that the company expected Breidablikk’s licensees to remain unaffected.
Sejersted also said future approvals would require greater consideration of individual projects in the context of overall production on the Norwegian continental shelf.
According to Nettavisen, MDG is calling for production to stop until the authorities have completed their reconsideration. The source material provides no confirmed timetable for that process or any indication of whether it will affect project schedules.