Aker Solutions puts the potential contract value at NOK 0.5–1.5 billion under its contract classification system. Subject to a final award, the company expects to record the order in its Renewables and Field Development segment in the fourth quarter of 2026.

The proposed work covers the topside, which weighs approximately 50,000 tonnes. Aker Solutions would undertake preparations and onshore handling, including receipt, dismantling and recycling. Equinor is the end client, while Allseas is to carry out the offshore removal lift using its heavy-lift vessel Pioneering Spirit.

Arrival expected between 2029 and 2031

According to Aker Solutions, the topside is expected to reach its Stord decommissioning facility between 2029 and 2031. The company estimates that dismantling and recycling would take about two years, with the workforce at the yard expected to peak at around 100 people.

The topside was constructed at Stord in 1975 and installed on the platform’s concrete gravity base in 1976, the company said. The letter of intent concerns the topside, rather than the concrete base.

The arrival window, work duration and peak workforce remain company estimates.