Wind Apex is expected to work alongside the installation vessel already assigned to the project. Dogger Bank Wind Farm says it could also undertake outstanding work on the wind farm’s other phases. The contract value has not been disclosed.

The assignment will be Wind Apex’s first campaign, Cadeler chief executive Mikkel Gleerup said in a press release.

Dogger Bank C represents the 1.2 GW third phase of the wider 3.6 GW Dogger Bank development, located approximately 130 kilometres off England’s north-east coast. Plans for the C phase specify 87 GE Vernova Haliade-X turbines, each rated at 14 MW.

SSE and Equinor each hold a 40% stake in the project, with Vårgrønn owning the remaining 20%. SSE is responsible for development, while Equinor is to operate the wind farm after completion.

Wind Apex is the third vessel in Cadeler’s A-class and is designed to install both foundations and turbines. Delivery from the shipyard is scheduled for the first half of 2027, according to Splash247, which reports a deck area of approximately 5,600 square metres.