The assessment covers the route from vessels to the reservoir on the Norwegian continental shelf. According to the article’s account of DNV’s findings, the main technical challenges have been identified and are considered manageable at the concept’s current stage of development.
Under the proposed arrangement, Höegh Evi would operate shuttle tankers carrying liquid CO₂ to the storage site. A transfer system and subsea pipelines would deliver the cargo to injection wells. Aker BP has not ruled out pipeline transport at a later stage.
A planned floating terminal would receive industrial emissions and prepare the CO₂ for shipment. The terminal was outside the scope of this feasibility assessment, although both the terminal and vessels previously received approval in principle from DNV, the article reports.
The first phase has a potential storage rate of up to 6 million tonnes of CO₂ a year. Total storage potential within the licence is estimated at 150 million tonnes.
Aker BP is targeting injection start-up around 2031 and an operating period exceeding 25 years. The schedule remains subject to subsequent investment decisions.