The awards comprise NOK 2 billion for Fortius Offshore Wind and NOK 1.94 billion for Fram Wind Solutions, under Enova’s funding competition for small-scale commercial floating offshore wind projects.

Each developer plans to install two turbines at the Rogaland test site within five years. The projects would have a combined capacity of approximately 74 MW. Enova estimates annual electricity generation at around 300 GWh.

Conditions for Fram funding

Fram Wind Solutions must meet several conditions to secure its funding. According to BW Offshore, an investment decision, financing and key supplier agreements must be in place within 24 months.

BW Offshore holds a 50% stake in Fram Wind Solutions, alongside Grieg Kapital with 35% and Fram Green Technology with 15%. The Fram project plans to use BW Ideol’s Damping Pool floating foundation.

The two projects are intended to test foundations for large turbines, mooring systems, and construction and operating methods.

According to Norwegian Offshore Wind, five companies sought a total of NOK 9 billion through the competition. Cost-effectiveness accounted for 70% of the assessment.