The case concerns auctions held in July 2019 and July 2020 for annual gas transmission capacity at PIR Pirineos, the interconnection point between France and Spain.

In January 2025, the sanctions committee of French energy regulator CRE fined both companies after concluding that they had coordinated their conduct to drive down short-term capacity prices, the report said.

In two rulings dated 10 November, Conseil d’État, France’s highest administrative court, found that coordination had not been proven. Among the factors it considered was Equinor’s record of regularly booking small capacity volumes at the border point since 2015, regardless of market conditions. The court consequently annulled Equinor’s penalty in full.

The finding against Danske Commodities over its own bidding remains in place. According to the report’s account of the rulings, those bids sent false or misleading signals about demand for annual capacity, breaching the EU’s REMIT market integrity rules. Removing the coordination finding reduced its fine by €1 million.

Danske Commodities maintains that its bids were legitimate but says it accepts the outcome and considers the case closed. According to the company’s comment cited in the report, the decision cannot be appealed.