The Norwegian-flagged vessel departed Australia on 23 October after fitting 26 buoyancy modules and trenching 30 kilometres of cable, Nexans said.
The connection runs approximately 135 kilometres between Barrow Island and the project’s floating field control station. Nexans said the 145 kV cable had been manufactured, tested and installed as a continuous length, without joints.
The station is intended to supply electricity to the seabed compressors and control their operation. When the contract was awarded in 2021, the compressors were planned for a water depth of about 1,400 metres. The compression system is intended to help maintain gas supplies to the facilities on Barrow Island that form part of the Gorgon development.
Work remaining before handover
Jointing is still required at both Barrow Island and the field control station. Rock stabilisation also remains outstanding along the final 28 kilometres of the route. According to Nexans, the client plans to carry out the final test, known as a soak test, in February 2027.
The installation work also included fitting approximately 200 metres of VIV strakes. These elements are designed to limit vortex-induced vibration along a steep section of the cable route.
Nexans Norway AS secured the contract to engineer, manufacture and install the cable in 2021. The contract value has not been disclosed.