The supply covers a 110 kV mass-impregnated cable system, according to Nexans.

Greek grid operator IPTO awarded the main project to Hellenic Cables. The planned link will connect the Dodecanese islands to the Greek mainland.

Nexans said the main connection has a capacity of 1 GW and a voltage of 320 kV. The project includes around 1,260 kilometres of subsea cable and 30 kilometres of land cable.

Work on Nexans’ mass-impregnated cable production lines and a seabed survey are already under way. The company expects the project to generate activity on the production lines from late 2026 to mid-2028.