The award was announced on 2 November, according to the document, which cites a Subsea7 contract announcement. The precise contract value has not been disclosed.

Subsea7’s scope covers engineering, procurement, construction and installation (EPCI) of production and gas-lift pipelines, together with associated subsea infrastructure. The production pipeline will use a pipe-in-pipe design, with installation to be carried out by vessels from Subsea7’s fleet.

Previously known as Kjøttkake, Lyra is planned as a tie-back to Gjøa using infrastructure at Nova. The field lies approximately 44 kilometres from the Gjøa platform.

Citing Splash247, the document describes a three-well subsea development with estimated recoverable resources of 37 million barrels of oil equivalent. Expected plateau production is approximately 20,000 barrels per day. Submission of the plan for development and operation to the authorities is expected soon, according to the document.

Project management and engineering are to be carried out in Stavanger, while pipeline assembly is planned at Vigra. Offshore work is scheduled across 2026, 2027 and 2028.

The award falls under the Aker BP Subsea Alliance, which also includes OneSubsea. The document states that Subsea7 received an advance commitment for long-lead equipment in December 2025.