The well is being drilled with the semi-submersible rig COSLProspector in production licence 636, where Vår Energi is operator. The licence is in the Gjøa area.
The Norwegian Offshore Directorate granted a drilling permit in July, and the Norwegian Ocean Industry Authority gave consent in September, according to the source draft.
An application to the Norwegian Environment Agency includes an option to drill appraisal well 36/7-7, named Sava Appraisal, if the exploration well yields results. The wells are subject to special coastal oil spill preparedness requirements. They are within 25 kilometres of the baseline and 24 kilometres from the nearest land at Værlandet in Askvoll.
Cerisa development
Cerisa was discovered in 2024, when its resources were estimated at 18–39 million barrels of recoverable oil equivalent.
The discovery is part of Gjøa Subsea Projects alongside Gjøa Nord and Ofelia. Vår Energi and its partners took an investment decision on the projects in June, according to the source draft.
Cerisa is planned to start production in the third quarter of 2027, with a tie-in to infrastructure at Gjøa and Duva. As of 11 November, the Sava well result had not been made public and the drilling completion date was unknown.