Belga cited reporting by Belgian newspapers De Tijd and L’Echo. The source document also notes that Energiwatch had reported the project’s suspension in October.

Equinor spokesperson Magnus Frantzen Eidsvold told the Belgian newspapers that inadequate demand was behind the postponement. The company intends to retain the work already completed in case the market for carbon capture and storage grows.

According to Belga, the pipeline was intended to carry 18 million tonnes of CO₂ a year from Flanders to Norway, starting in 2030. The plans included a possible increase in annual capacity to 27 million tonnes. The proposed route ran from Zeebrugge to depleted gas fields on the Norwegian continental shelf.

Project partner Fluxys told Le Soir that work on a compressor station in Zeebrugge was continuing. The Belgian gas network operator is also examining alternative CO₂ export routes, including CarbonConnect, a proposed connection between Zeebrugge and storage sites in the UK sector of the southern North Sea.